Current Projects

Measure HH Bond Projects

Building the Future Through Strategic Campus Improvements
$3.5 Billion Investment

Current Projects

HH-E-001-009
 
4343 Ocean View Blvd, San Diego, CA 92113
 
A transformative renovation of the historic ECC theatre, which has hosted cultural icons including Whoopi Goldberg, Maya Angelou, and Stevie Wonder. The project will modernize theatre facilities, create a new "Living Archive" cultural center, and enhance community spaces.
 

Project Timeline

  • Dec 2024 - Design Completion
  • May 8, 2025 - Ground Breaking
  • May/Jun 2025 - Construction Start
  • Jan 2027 - Expected Completion
HH-E-002-003
 
7350 Armstrong Pl, San Diego, CA 92111
 
Targeted upgrades to the 38,500 square-foot facility including heating and cooling improvements, exterior modifications, accessibility compliance, roofing enhancements, and main entry reconfiguration for security and visibility.
 
Project Timeline
  • Programming Completion: September 2025
  • Design Completion: August 2026
  • DSA Approval: November 2026
  • Construction Completion: July 2028 (Tentative)
 
HH-E-003-001
 
4343 Ocean View Blvd, San Diego, CA 92113
 
Renovation and modernization of training facilities including welding booths with modern equipment, new air quality extraction system, roofing, classroom and office spaces, outdoor yard, and storage areas.
 
Project Timeline
  • Programming Completion: January 2026
  • Design Completion: August 2026
  • DSA Approval: January 2027
  • Construction Completion: July 2028
HH-E-004-011
 
3249 Fordham St, San Diego, CA 92110
 
New building construction along with modernization of a portion of the existing facility to expand and enhances existing programs.
 
Project Timeline
  • Programming Completion: December 2026
  • Design Completion: November 2026
  • DSA Approval: July 2027
  • Construction Completion: November 2029
HH-E-005-006
 
4343 Ocean View Blvd, San Diego, CA 92113
 
Renovation of existing spacesto a new Ceramics studio which will enhance student learning, safety and program capacity.
 
Project Timeline
  • Programming Completion: August 2025
  • Design Completion: December 2025
  • DSA Approval: July 2026
  • Construction Completion: April 2027
HH-E-007-005
 
4343 Ocean View Blvd, San Diego, CA 92113
 
Critical structural enhancements across 52,600 square feet. Voluntary seismic improvements implemented in three phases: Theatre Renovation, Community Room Renovation, and remaining facility areas.
 
Project Timeline
  • Programming Completion: January 2026
  • Design Completion: June 2026
  • DSA Approval: January 2027
  • Construction Completion: October 2027
Project Timeline
 
  • Programming Completion: May 2025
  • Design Completion: May 2026
  • DSA Approval: January 2027
  • Construction Completion: October 2027
The project consists of a new campus that will accommodate in-demand programs within the community. 
 
Project Timeline
  • Programming Completion: April 2026
  • Design Completion: April 2027
  • DSA Approval: February 2028
  • Construction Completion: July 2030
The existing campus will be undergoing tenant improvements to better support its existing programs.
 
Project Timeline
  • Fall 2025 - Design Kickoff
Jacqueline Sabanos

Jacqueline Sabanos

Vice President, Administrative Services

[email protected]
Default user image

Anthony Vargas

Director, College Facilities and Operations

[email protected]
Default user image

Mariana Toma

Campus Liaison for Measure HH Region 1

[email protected]